September 1, 2017

September 2017

September 2017   We break ground on Northwest Parking Garage in Margate, work will need about 1,000 CY of concrete for foundations and will have 4 […]
August 1, 2017

August 2017

August 2017   Foundations work on Lemongrass Bistro @ Wellington Green Mall have started. The shell on Peppertree job is now completed.  
July 1, 2017

July 2017

July 2017   Foundations on Peppertree are completed and CMU work have started. We received a Safety Training regarding new Silica Rule from OSHA. All Contract […]
June 1, 2017

June 2017

June 2017   We have started placing grout underneath of base plates for multiple steel items on Renewco Project, this activity will have thousands of bases […]
May 1, 2017

May 2017

May 2017   Sidewalks connecting buildings are now completed on Renewco Project. Preparing submittals for 4 Parking Garages (Foundation, SOG and Wash Concrete) in Aventura, Margate, […]
April 1, 2017

April 2017

April 2017   All the SOMD – Slab on Metal Decks were completed on Pulping and Molding Buildings. On Renewco Buildings, 54 Miscellaneous concrete items are […]
March 1, 2017

March 2017

March 2017   Apron Concrete Pavement using 4,000 psi with fiber was placed and finished on Renewco Bagasse Area – 38,000 SF / 947 CY in […]
February 1, 2017

February 2017

February 2017   Exteriors for Paragon Theaters including heavy duty Concrete, sidewalks, colored concrete and bollards were completed. Octagonal shape concrete pads were formed and placed […]
January 1, 2017

January 2017

January 2017   Work for 4 different buildings (Molding, Pulping, Office & Bagasse) and Tanks Farm area are in progress at Renewco Project. Color Concrete SOG […]