June 2017
June 1, 2017August 2017
August 1, 2017July 2017
- Foundations on Peppertree are completed and CMU work have started.
- We received a Safety Training regarding new Silica Rule from OSHA.
- All Contract work on Renewco Project is now completed, 41,000 MH and more than 7,000 CY of concrete have been placed. Still more additional work regarding miscellaneous items to go.